In short

Piling and ground improvement are the two answers to ground that will not carry the structure: transfer the load through it, or make the ground stronger. Piles are bored, driven or screwed; improvement covers preload, stone columns, soil mixing and dynamic compaction. Ground conditions govern the choice, and the contract clause on founding depth governs who pays when reality differs.

A contractor prices a pump station on a coastal site. The structure is straightforward, the excavation is shored, and the drawings show sixteen piles to a nominated founding level. The piling is sublet on a rate per metre against the scheduled depths and the contractor moves on to the parts of the job it understands.

On site, nine of the sixteen reach the nominated level and stop short of the required capacity. The engineer instructs deeper piles. The schedule of depths was indicative. The specification says founding depth is to be confirmed on site at the contractor’s risk. The rig is on standby at a day rate while three parties argue about a sentence nobody read at tender.

Foundations are where a civil job’s ground risk concentrates. This guide covers the methods, what the geotechnical information can and cannot tell you, how the risk is allocated, and what a rate is actually made of. The excavation and shoring that usually sits alongside it is covered in our guide to temporary works and excavation support.

Two answers to the same problem

The problem is always the same: the ground near the surface cannot carry the load, or will settle too much, or will not stay where it is. There are only two families of answer.

PilingGround improvement
What it doesCarries the load past the weak material to something competentMakes the weak material stronger, stiffer or denser
Typical triggerConcentrated structural loads — bridges, pump stations, tanks, retaining structuresDistributed loads over area — embankments, pavements, hardstands, tank farms
VerificationLoad testing and integrity testing on individual pilesSettlement monitoring and in-situ testing over an area
Programme shapeDiscrete, rig-based, fast once mobilisedOften slow — some methods need months of waiting
Who does itSpecialist piling contractors with their own plantSometimes a specialist, sometimes your own earthworks crew
Where the risk sitsFounding depth and obstructionsWhether the design settlement is actually achieved, and when

The distinction matters commercially because the two families fail differently. A pile that will not found is an immediate, visible, expensive stoppage. Ground improvement that has not worked is discovered slowly, through monitoring, often after you have built on top of it — which makes it the harder of the two to recover from.

The pile types you will actually meet

There are dozens of proprietary systems. On Australian civil work an SME meets a handful.

TypeHow it is installedSuitsWatch for
Bored piles (cast in situ)A hole is drilled, reinforcement placed and concrete poured, with casing or fluid support where the hole will not standLarger diameters, variable ground, sites where vibration is unacceptableSpoil volume and classification; concrete overbreak; hole stability below the water table
Continuous flight auger (CFA)A hollow auger is drilled to depth and concrete pumped through the stem as it is withdrawn, with reinforcement pushed in afterFast production in reasonably uniform groundReinforcement depth is limited; the process is verified by monitoring data, not by looking at it
Driven piles (precast or steel)A preformed pile is hammered or vibrated to depthWhere a driving record gives immediate capacity evidence; marine and soft-soil sitesNoise and vibration; pile damage; refusal on obstructions; lengths ordered before you know the depth
Screw or helical pilesA steel shaft with helices is torqued into the groundLight to moderate loads, restricted access, fast installation with torque correlationCapacity correlation is method-specific; not suited to obstructed ground
Continuous-cased and drilled systemsCasing advanced with the drill to hold the hole openCollapsing ground and high groundwaterSlower and dearer; usually a response to a problem rather than a first choice

Two practical distinctions are worth holding onto. Displacement versus replacement. A driven or screwed pile displaces soil sideways; a bored pile removes it. Displacement generates vibration and can heave adjacent ground and services; replacement generates spoil you have to classify and cart. Neither is free, and the site usually decides which cost you would rather carry.

What you can see afterwards. A driven pile gives you a driving record as it goes in. A bored or CFA pile is concrete in a hole nobody will ever look at, which is why the verification regime in §06 exists and why the monitoring records are a contractual deliverable rather than a formality.

Ground improvement: fixing the ground instead

Where the load is spread over an area rather than concentrated at points, improving the ground is often cheaper than piling it — and on large earthworks platforms it is frequently the only economic answer.

MethodWhat it doesThe catch
Preload and surchargeFill is placed to force settlement before you build, then removedTime. Consolidation can take months, and it sits on the critical path
Wick drains (vertical drains)Installed with surcharge to shorten the drainage path and speed consolidationAdds cost to buy programme; needs a settlement monitoring regime to prove completion
Stone columnsColumns of compacted aggregate that stiffen and drain the soil massNot suited to very soft soils without a supporting method; aggregate supply is a real cost
Deep soil mixingBinder is mixed into the soil in place to form treated columns or blocksSpecialist plant; verification is by coring and testing, which takes time
Dynamic compactionA heavy weight is dropped repeatedly to densify granular fillVibration, and a standoff distance from anything you care about
Rolling and impact compactionHeavy compaction plant densifies fill in placeEffective depth is limited; verified by testing rather than assumption
Geosynthetic reinforcementGeogrid or geotextile spreads load and separates layersCovered in full in our guide to geosynthetics in civil construction

The programme point is the one contractors underestimate. Preload and wick drains buy strength with time, and time is the thing a tender programme has least of. A design that assumes a six-month surcharge period on a twelve-month contract is not a foundation decision, it is a programme decision, and it has to be visible in the tender programme rather than discovered in month three. Our guide to writing a construction program for tenders covers showing that kind of dependency properly.

How the choice is actually made

On most civil jobs the method is nominated in the design and you are pricing it, not selecting it. That does not make the reasoning irrelevant — it is exactly what tells you whether the nominated method is sensible, and therefore whether to price it straight, price an alternative, or ask a question before close.

  • Is the load concentrated or spread? Points of high load push toward piles; area loading pushes toward improvement.
  • How deep is competent material, and is it consistent? Shallow and consistent favours improvement or shallow footings. Deep and variable favours piling.
  • How much settlement can the structure tolerate, and over what period? This is the question that most often forces piling on a job that looked like an improvement site.
  • What is the programme? If there is no time for consolidation, methods that need time are out regardless of cost.
  • What is next door? Vibration-sensitive neighbours, shallow services or existing structures rule out whole families of method before any engineering is done.
  • What can get to the site? Rig size, headroom, access width and working platform capacity. A working platform that will not carry the rig is its own piece of temporary works.

That last point is routinely missed at tender. A piling rig needs a designed working platform, and building it — and removing it — is a real cost that belongs in your price rather than in the piling subcontractor’s assumptions.

Where the geotechnical report stops helping

The geotechnical report is the most important document in a piling package and the most commonly over-read.

  • Boreholes are points, and piles are somewhere else. Four boreholes on a site with sixteen piles means twelve piles are founded on interpolation. On variable ground, interpolation is a hypothesis.
  • Depth of investigation matters more than the number of holes. An investigation terminated at ten metres tells you nothing about a pile designed to found at fourteen.
  • Obstructions are almost never found by a borehole. Old footings, buried slabs, abandoned services, rubble fill and boulders are exactly the things a 100 mm hole misses and a pile finds.
  • The report is usually provided for information, not warranted. Read the transmittal wording and the contract’s treatment of provided information before you rely on it.
  • Factual and interpretive are different documents. Borehole logs and test results are facts; the recommendations built on them are opinion, and the contract may treat them very differently.

The practical response at tender is not to distrust the report but to be explicit about what you priced on: which document, which boreholes, what founding assumption, and what you have allowed for if it differs. That statement is worth more later than any amount of general qualification, because whether a condition is a latent condition turns partly on what a competent contractor should have inferred from the information provided.

Testing: how anyone knows it worked

Because a finished pile is invisible, the testing regime is the product. It is specified, it is priced, and it sits on the programme.

TestWhat it tells youProgramme effect
Static load testDirect measurement of capacity under load — the most definitive evidence availableSlow and expensive to set up; usually a small number of piles, often a preliminary test pile
Dynamic testingCapacity inferred from instrumented measurement during driving or restrikeFast; done on a proportion of piles as production proceeds
Integrity testingWhether the shaft is continuous and sound — not capacityQuick, routinely applied across many or all bored piles
Installation records and monitoring dataFor CFA and bored piles, the concrete volume, pressures and depths that show what happenedProduced automatically; the deliverable is getting it into the records
Preliminary or sacrificial test pileProves the design and method before production startsAn additional mobilisation, but it converts the largest unknown into a known before the rig is on rate

Two commercial notes. A preliminary test pile is usually money well spent and is frequently the cheapest way to stop a founding-depth dispute before it exists. And testing generates hold points — a pile cap cannot proceed over an untested or failed pile, so the test regime belongs in the inspection and test plan and in the programme, not in a pile of paperwork at the end.

What goes wrong, and what it costs

FailureWhat it isConsequence
Premature refusalThe pile stops on an obstruction well above design founding levelRedrill, relocate, or break out the obstruction. Almost always a variation argument
Founding deeper than scheduledCompetent material is lower than the drawings assumedMore metres, more concrete, more time — and the risk clause decides who pays
Hole collapse or neckingA bored hole closes before or during the pourDefective pile, integrity test failure, replacement pile and a redesigned cap
Concrete overbreakSubstantially more concrete than the theoretical volumeDirect cost, and a signal that the hole is not the shape anyone assumed
Verticality or position out of toleranceThe pile is not where the cap needs itCap redesign, additional piles, engineering assessment
Pile damage during drivingHead or toe damage, or a cracked precast sectionRejection and replacement; re-drive on a new position
Heave of adjacent pilesDisplacement piling lifts piles already installedRe-drive of completed work; monitoring obligation across the whole group
Service strikeThe rig hits an unlocated assetCovered in full in our guide to underground services and utility strikes

The economics of the first two rows are what make piling different from most civil work. The rig is the expensive thing, and it is idle while the argument runs. A dispute that would cost a week of correspondence on an earthworks job costs a week of standby here, which is why the risk clause in §08 is worth more attention than the rates.

The clause that decides who pays

Read the specification for how founding depth is treated. It usually falls into one of these, and the difference between them is the whole commercial position.

  • Scheduled depths, remeasured. Depths are indicative, you are paid for what is installed at scheduled rates. The fairest arrangement and the one to push for — but check that the rate schedule has bands, because a rate built for ten metres does not hold at eighteen.
  • Fixed depths, lump sum. You carry the risk of depth entirely. Only sensible where the ground is genuinely well understood, and rarely is.
  • Founding on a described stratum, at the contractor’s risk. The most dangerous version: the obligation is a condition, not a depth, and the depth needed to meet it is yours to find and fund.
  • Provisional quantity or provisional sum. Reasonable, provided the adjustment mechanism and the rates are agreed up front — see our guide to bills of quantities, provisional and PC sums.

Three further provisions repay reading before you price. Obstructions: is removing them a variation, or included? Standby: is rig standby payable when you are held up by the principal, the engineer, or a test result? Failed piles: who pays for a replacement pile where the ground, not the workmanship, caused the failure? A package with an adverse answer to all three is a package to price with a visible risk allowance and to record in the tender risk register.

What a piling rate is made of

A rate per metre hides most of the cost, which is why comparing two piling quotes on the metre rate alone is unreliable.

ElementVaries withNote
Mobilisation and demobilisationNothing — fixed per rig, per visitDominant on a small pile count. Two visits cost roughly twice one
Working platformGround conditions and rig weightA designed platform, built and later removed. Frequently omitted from both sides of the quote
Rig timeMetres, diameter, groundThe only genuinely per-metre element
Rig moves between positionsPile spacing and site layoutScattered piles cost far more per pile than a tight group
Concrete and reinforcementVolume, including overbreakTheoretical volume is a floor, not an estimate
Spoil handling and disposalVolume and classificationA waste classification question, not a cartage question
Casing, fluid support and disposalHole stability and groundwaterSupport fluid has its own handling and disposal cost
TestingThe specified regimeStatic tests in particular are a mobilisation of their own
Standby and delayThird parties, weather, test resultsThe item most often left out and most often incurred
Cut-off and trimmingPile countBreaking down to cut-off level, and carting the debris, is real work

The structural point is the same one that applies to a trenchless crossing: separate the fixed and the variable elements rather than burying mobilisation in the metre rate. If the pile count drops you lose the recovery; if it rises you over-recover and invite a challenge. The general principle is covered in schedule of rates versus lump sum.

Vibration, noise and the neighbours

Driven piling and dynamic compaction are among the most disruptive activities in civil construction, and on a suburban or industrial site the constraint is usually the neighbours rather than the engineering.

  • Pre-condition surveys before you start. Photographic and written records of adjacent structures. Without them, every pre-existing crack becomes yours.
  • Vibration monitoring with trigger levels and a defined response. Trigger-and-response is the structure that both regulators and evaluators look for.
  • Working hours, which are frequently narrower than the site’s general hours for high-noise activity, and which directly set your production rate.
  • A method change held in reserve. Where vibration limits may bind, knowing in advance that bored piles are the fallback — and what they cost — is worth more than arguing about the limit.
  • Notification and complaint handling, which is a stakeholder obligation rather than a technical one.

The monitoring and management side is covered in full in our guide to noise, vibration and dust management, and the neighbour-facing side in community and stakeholder engagement plans.

Subletting to a piling contractor

Almost no civil SME owns piling plant, and almost none should. The package is sublet, which makes the letting the decision that matters. The general discipline is in our guide to engaging and managing subcontractors; these are the piling-specific questions.

  • What ground information have you priced on, and what did you assume where it is silent?
  • What depth is included, and what is the rate beyond it — in bands?
  • Who builds and removes the working platform, and who designs it?
  • What happens on refusal: who pays for the attempt, the obstruction removal, and the replacement pile?
  • Are standby rates stated, and what triggers them?
  • Who takes spoil away, and who classifies it?
  • What testing is included, and who pays for a retest after a failure?
  • What tolerance on position and verticality are you offering, and who wears a cap redesign if it is exceeded?
  • What are your insurance limits, and do they respond to damage to adjacent property from vibration or heave?

As always, get the ground assumption into the subcontract rather than leaving it in an email. A quote assuming “no obstructions, founding at scheduled depth” is a quote for a job that may not exist, and the gap between the risk you carry upward and the risk you passed down is yours.

Writing the methodology

A piling methodology is one of the easier places for an evaluator to tell whether a bidder has done this before, because the failure modes are specific and the generic version is obvious.

  • Why this method for this ground, referenced to the actual boreholes and the actual constraint.
  • The working platform: who designs it, what it is built from, and how it is certified.
  • Sequence and set-out, including how position and verticality are controlled and checked.
  • The test regime and the hold points, with the response when a test fails.
  • Vibration and settlement monitoring, with trigger levels and the action at each level.
  • The contingency: what happens on refusal, and what the fallback method is. Naming it before it is needed is the strongest signal in the document.
  • Spoil and concrete logistics, which on a tight site is the thing that actually governs production.
  • Records: the pile log, the monitoring data, and the as-constructed positions.

The craft of writing it — structure, evidence and answering the criterion rather than describing yourself — is covered in our guide to writing a construction methodology statement.

Checklist

  • Is there a borehole near each pile group, taken below the design founding level?
  • Does the specification treat founding depth as scheduled and remeasured, or as a condition at your risk?
  • Are the rate bands adequate for depths well beyond the scheduled ones?
  • Is obstruction removal a variation or included?
  • Is rig standby payable, and on what triggers?
  • Who pays for a replacement pile where the ground caused the failure?
  • Has the working platform been designed, priced and programmed — including its removal?
  • Is mobilisation priced separately from the metre rate?
  • Have spoil volume, classification and disposal been priced rather than assumed?
  • Is the testing regime in the programme and in the ITP as hold points?
  • Has a preliminary test pile been considered where founding depth is uncertain?
  • Are pre-condition surveys of adjacent structures programmed before work starts?
  • Are vibration trigger levels, monitoring and responses defined?
  • Has every service on the pile positions been proved, not just searched for?
  • Does the subcontract state the ground assumptions in writing?
  • On ground improvement, is the consolidation or verification period on the tender programme?

The short version

  • Two families solve the same problem: carry the load past bad ground, or make the ground better. Concentrated loads push toward piles, area loads toward improvement.
  • Piling fails loudly and immediately; ground improvement fails quietly and late, which makes it harder to recover from.
  • Displacement methods make vibration; replacement methods make spoil. The site decides which cost you carry.
  • A bored pile is invisible once poured, so the testing and monitoring records are the product, not paperwork.
  • Boreholes are points and piles are somewhere else. Obstructions are almost never found by an investigation.
  • State at tender what ground information you priced on and what you assumed. It matters later for any latent conditions argument.
  • Preload and wick drains buy strength with time. If the programme has no time, those methods are out whatever they cost.
  • Read how founding depth is allocated. “Found on the described stratum at the contractor’s risk” transfers the largest risk on the package.
  • Check three clauses before pricing: obstructions, standby, and who pays for a pile that fails because of the ground.
  • Mobilisation, the working platform, rig moves, spoil and testing are most of the cost. A metre rate alone tells you very little.
  • A preliminary test pile is usually the cheapest way to convert the biggest unknown into a known before the rig is on rate.
  • Do pre-condition surveys before driving anything, and set vibration triggers with a defined response.
  • When subletting, get the ground assumptions into the subcontract, not into an email.

Sources and further reading

This guide is general information for Australian civil construction businesses and is not engineering, geotechnical or safety advice. Pile design, ground improvement design, working platform design and the assessment of vibration effects on adjacent structures are engineering matters requiring site-specific design by a suitably qualified engineer. Testing regimes, tolerances, founding criteria and acceptance are set by the project specification and the design, and differ between projects, authorities and structure types. Whether particular ground conditions give rise to a claim depends on the contract and the information provided. Always work from the project geotechnical report, the approved design and current specialist advice. Information is current as at September 2026.

Writing a tender? Let’s write it together.

HoursMon–Fri 7am–5pm AEST